Roadwork details
Location
A9 Calvine SB - Convoy Works
Direction
Southbound
Starting
24th of March 2024, 7:00pm
Ending
2nd of May 2024, 6:00am
Days & times affected
Week commencing 22nd Apr
Early Morning (00:00 - 06:00)
Monday, Tuesday, Wednesday, Thursday, Friday.
Evening (18:00 - 00:00)
Monday, Tuesday, Wednesday, Thursday, Sunday.
Week commencing 29th Apr
Early Morning (00:00 - 06:00)
Monday, Tuesday, Wednesday, Thursday.
Evening (18:00 - 00:00)
Monday, Tuesday, Wednesday.
Roadwork description
Works:
Lining Works, Resurfacing
Traffic Management:
Convoy Working (10mph)
Diversion Information:
Night Closure of the B847 Junction with Diversion.
NB Traffic (1) – To be diverted to the House of Bruar Junction and then SB to the A924 Pitlochry Junction and then back up the A9 NB.
NB Traffic (2) – To be diverted to Kingussie and then back down the A9 SB to House of Bruar then the B847.
SB Traffic – To be diverted to the House of Bruar Junction, then continue SB as usual.
Lining Works, Resurfacing
Traffic Management:
Convoy Working (10mph)
Diversion Information:
Night Closure of the B847 Junction with Diversion.
NB Traffic (1) – To be diverted to the House of Bruar Junction and then SB to the A924 Pitlochry Junction and then back up the A9 NB.
NB Traffic (2) – To be diverted to Kingussie and then back down the A9 SB to House of Bruar then the B847.
SB Traffic – To be diverted to the House of Bruar Junction, then continue SB as usual.